Pakistan, the real estate market is thriving with a projected growth rate of over 5% annually through 2028. With a housing deficit exceeding 10 million units, building a 10 Marla house (approximately 2,250-2,722 sq ft, costing PKR 16.3-20 million) is a popular choice for homeowners in Lahore, Islamabad, and Karachi. At Afaq Ahmad Constructions, we’ve streamlined the process for countless projects. This blog offers a step-by-step timeline for building a 10 Marla house in 2025, ensuring efficiency, quality, and cost management amid rising material prices and labor demands.
Why a Detailed Timeline Matters in 2025
Lahore’s diverse climate—40°C summers, 600-800 mm monsoons, and mild winters—impacts construction schedules, as noted in our weather blog. The Pakistan Building Code (PBC) 2021 and Green Building Code 2023 enforce strict standards, while material costs (e.g., cement at PKR 1,060/bag) and labor rates (PKR 450-500/day) have risen by 5-7% in 2025, per our cost and timeline blogs. A well-planned timeline saves 2-4 weeks (PKR 50,000-100,000) and avoids overruns of PKR 500,000-1 million, making it essential for a successful 10 Marla build.

Step-by-Step Timeline for Building a 10 Marla House
Phase 1: Pre-Construction Planning (Weeks 1-8, 2 Months)
- Duration: 8 weeks.
- Activities:
- Weeks 1-2: Define budget (PKR 16.3-20 million) and secure financing (e.g., HBL loan at 8-10% interest), including a 10-15% buffer (PKR 1.6-3 million), per our cost guide.
- Weeks 3-4: Choose location (e.g., DHA Lahore at PKR 4,000-5,500/sq ft or Johar Town at PKR 3,500-4,500/sq ft) and purchase land (PKR 1.5-2 crore), verifying titles with LDA, per our location blog.
- Weeks 5-6: Hire architect (PKR 20,000-50,000) and engineer (PKR 30,000-70,000) for design (e.g., 3-bedroom, double-story layout), using CAD software, per our trends blog.
- Weeks 7-8: Finalize plans and obtain approvals from LDA (PKR 38/sq ft scrutiny + 3% TIP tax, PKR 300,000-500,000) or DHA (20-day process), per our approvals blog.
- Milestone: Approved design and permits.
- Cost: PKR 350,000-620,000.
- Tip: Start in dry months (October-March) to avoid monsoon delays.

Phase 2: Site Preparation and Foundation (Weeks 9-14, 6 Weeks)
- Duration: 6 weeks.
- Activities:
- Weeks 9-10: Clear land, level soil, and set boundaries (PKR 50,000-100,000), per our site prep insights.
- Weeks 11-14: Lay reinforced concrete foundation (RCC at PKR 400-600/sq ft, PKR 900,000-1.35 million), including waterproofing (PKR 50,000-100,000) for monsoon resilience.
- Milestone: Completed foundation.
- Cost: PKR 1-1.55 million.
- Tip: Use tarps (PKR 5,000-10,000) to protect materials from weather.

Phase 3: Grey Structure Construction (Weeks 15-30, 16 Weeks)
- Duration: 16 weeks.
- Activities:
- Weeks 15-20: Erect walls with fly ash bricks (PKR 10-15 each, PKR 300,000-500,000) and install lintels, per our bricks blog.
- Weeks 21-25: Build roof with RCC slab (PKR 500-700/sq ft, PKR 1.12-1.57 million) and install beams.
- Weeks 26-30: Complete structural framework, including staircases and balconies.
- Milestone: Waterproofed grey structure.
- Cost: PKR 1.42-2.07 million.
- Tip: Monitor weekly with a supervisor (PKR 30,000-50,000/month), per our QA blog.

Phase 4: Finishing Works (Weeks 31-42, 12 Weeks)
- Duration: 12 weeks.
- Activities:
- Weeks 31-34: Install plastering (PKR 100-150/sq ft, PKR 225,000-337,500) and flooring (tiles at PKR 200-500/sq ft, PKR 450,000-1.125 million).
- Weeks 35-38: Apply paint (PKR 1,500-2,000/liter, PKR 150,000-200,000) and install doors/windows (PKR 300,000-500,000).
- Weeks 39-42: Add fixtures (e.g., lights at PKR 500-1,000 each, PKR 50,000-100,000) and final touches.
- Milestone: Interior and exterior finishes completed.
- Cost: PKR 1.175-2.2625 million.
- Tip: Use heat-resistant finishes (PKR 150-300/sq ft) for Lahore’s climate.

Phase 5: Mechanical, Electrical, and Plumbing (MEP) (Weeks 43-48, 6 Weeks)
- Duration: 6 weeks.
- Activities:
- Weeks 43-44: Install plumbing (PPRC pipes at PKR 150-200/meter, PKR 300-500/sq ft, PKR 675,000-1.125 million), per our plumbing blog.
- Weeks 45-46: Set up electrical wiring (PKR 200-400/sq ft, PKR 450,000-900,000) and panels.
- Weeks 47-48: Test systems and fix leaks or faults.
- Milestone: Fully functional MEP systems.
- Cost: PKR 1.125-2.025 million.
- Tip: Hire certified technicians to avoid PKR 100,000-200,000 in rework.

Phase 6: Final Inspections and Handover (Weeks 49-50, 2 Weeks)
- Duration: 2 weeks.
- Activities:
- Week 49: Conduct structural integrity checks, leak tests, and PBC 2021 compliance review with an inspector (PKR 20,000-50,000).
- Week 50: Address minor fixes, obtain occupancy certificate from LDA/DHA, and hand over keys.
- Milestone: Ready for occupancy.
- Cost: PKR 20,000-50,000.
- Tip: Document with photos for records, per our supervision blog.

Total Timeline and Cost Overview
- Total Duration: 50 weeks (approximately 11.5 months), aligning with our timeline blog’s 24-40 week range for optimized projects.
- Total Cost: PKR 5.27-8.5775 million (construction only, excluding land at PKR 1.5-2 crore), totaling PKR 16.3-20 million for a turnkey 10 Marla home.
- Regional Variation:
- Lahore (PKR 3,000-4,500/sq ft): 28-32 weeks.
- Islamabad (PKR 3,500-4,800/sq ft): 30-34 weeks.
- Karachi (PKR 3,800-5,000/sq ft): 28-32 weeks.
- Savings: PKR 500,000-1 million with efficient planning, per our cost guide.
Challenges and Solutions in 2025
Challenges
- Inflation: Material costs may rise 5-10% mid-year, adding PKR 500,000-1 million, per our cost blog.
- Weather Delays: Monsoons (July-August) add 2-4 weeks, per our weather blog.
- Labor Shortages: Skilled workers delay progress by 1-2 weeks.
- Approval Delays: Bureaucracy extends timelines by 2-4 weeks.
Solutions
- Budget Buffer: Allocate 10-15% (PKR 1.6-3 million), per our cost guide.
- Weather Planning: Schedule outdoor work in dry months (October-March), saving PKR 200,000-400,000.
- Labor Training: Afaq Ahmad Constructions provides skilled crews.
- Expedited Approvals: Use our network to reduce approval time.

2025 Market Context
- Demand: High in Lahore Smart City, DHA, and Bahria Town for 10 Marla homes.
- Trends: Efficiency, sustainability, and modern designs dominate, per our trends blog.
- Costs: Inflation and labor shortages impact budgets.
- Solution: Trust Afaq Ahmad Constructions for timeline management.

Visualizing Your Timeline
Imagine a 10 Marla home in Johar Town with a solid foundation (our villa image), a Bahria Town house with finished interiors (our bungalow image), and a DHA Lahore estate ready for handover (our roofing image). Afaq Ahmad Constructions ensures a smooth process.
The Role of Afaq Ahmad Constructions
At Afaq Ahmad Constructions, we optimize your timeline:
- Expert Planning: We schedule every phase.
- Quality Assurance: We meet PBC 2021 standards.
- Support: We manage delays and costs.
Visit https://afaqahmadconstructions.com/ to start your 10 Marla build today!

Conclusion
Building a 10 Marla house in 2025 follows a 50-week timeline: 8 weeks for planning, 6 weeks for site prep and foundation, 16 weeks for the grey structure, 12 weeks for finishing, 6 weeks for MEP, and 2 weeks for inspections, costing PKR 5.27-8.5775 million (total PKR 16.3-20 million with land). Efficient planning with Afaq Ahmad Constructions saves PKR 500,000-1 million and 2-4 weeks, ensuring a high-quality home. Contact us now to begin!